FJT Power Logo
FJT POWER
Generator Solution Supplier
Johor, Malaysia Hyperscale Data Center

Dealer-Built Cummins Packages for a Hyperscale Data Center Campus

Six QSK60-powered packages delivered in 28 weeks, meeting the same acceptance standard as OEM factory units on a multi-vendor campus.

Hyperscale data center campus under construction in Johor, Malaysia
FJT Scope 2500kVA × 6
Engine Platform Cummins QSK60
Firm Capacity 10MW · 5+1
Site Delivery 28 weeks

The Context

This campus is part of the rapid hyperscale expansion in Johor's data center corridor. Its standby plant was procured through multiple supply channels: Caterpillar factory packages, Cummins factory packages and Cummins-powered generator sets packaged and delivered by FJT POWER. This structure is increasingly common when a single OEM channel cannot support the full construction schedule.

FJT POWER was selected for the mechanical plant power block. At contract stage, factory-package lead times for large-bore engines were above 50 weeks, while the construction program required six complete units on site in less than 30 weeks. The decision therefore depended on three measurable factors: delivery schedule, commercial efficiency and proof that package quality would be assessed against exactly the same acceptance standard.

Campus overview: the multi-vendor standby plant includes OEM factory packages and independent power blocks. FJT POWER's scope was the six-unit Cummins-powered mechanical plant block.

The Challenge: Same Spec, No Concessions

Using an independent package builder did not relax the project specification. The owner's engineering and commissioning teams required the FJT block to be documented, tested and integrated using the same process applied to the adjacent OEM-supplied units.

Documented genuine drivetrain

Cummins QSK60 G-Drive engines and OEM alternators were submitted with complete serial-number traceability at contract stage, not deferred until delivery.

Identical witnessed FAT

The owner's commissioning agent witnessed 100% and 110% load runs, ISO 8528-5 Class G3 transient response and fuel-consumption verification using the same test sheets as the factory packages.

Campus-standard controls interface

Paralleling controllers and the complete SCADA points list matched the campus specification, allowing operators to supervise the FJT block through the same monitoring environment.

Tropical design baseline

Cooling was designed for 40°C ambient operation without derating, supported by type-tested enclosures and two-stage air filtration.

The Solution

Schedule

Engines and alternators were secured against existing allocation while packaging engineering proceeded in parallel. Contract to site delivery: 28 weeks.

Block Architecture

Five running units plus one redundant unit provide 10MW firm capacity to the mechanical plant through an independent 11kV bus.

Fuel Integration

Individual day tanks connect to the campus bulk fuel farm and polishing system, supporting the site-wide 12-hour autonomy requirement.

Commissioning Results

≤10s

All six units reached rated voltage and frequency within the required start window on every witnessed run.

8 hours

The 100% load-bank heat run at 36°C ambient maintained all specified thermal margins.

100% / 110%

Rated and overload testing, transient response and fuel verification completed under third-party witness.

0

Package-build-quality punch-list items recorded at handover.

The integrated systems test was passed alongside the OEM-supplied blocks, under the same protocol and with the same witnesses.

Why the Owner Used an Independent Package Builder

The result was a mechanical-plant power block that was indistinguishable from the adjacent factory units in performance, documentation and controls integration, but arrived in roughly half the prevailing factory-package lead time. The procurement decision did not require the owner to trade quality for schedule: traceability and identical acceptance testing made package quality measurable before handover.

This is the practical role of a qualified independent packager on a hyperscale program: secure genuine powertrain components, engineer the package around the campus standard, accept third-party witnessed testing and remove schedule risk without creating cross-vendor paralleling dependency.

Next Project

N+1 Standby Power for a 400-Bed Acute Care Hospital

More languages · automatic translation

English, Indonesian and Russian have dedicated pages in the header menu. Other languages use automatic translation.